Economic Development Report
To
Enfield Town
Council
Raymond L. Warren,
Director of Economic Development September
2005
The new MassMutual
campus on Bright Meadow Boulevard is advancing toward
completion. The company is planning a
public ceremony in October to showcase the facility.
Visitors will observe a significant
development project that includes a new 1,500 car parking garage, completely
remodeled office space, the largest cafeteria in the area, and a reconfigured
entrance area. Best estimates are that
building acquisition, renovations, and new construction represents a $75
million investment in Enfield. The project will be completed in
May 06.
A project of this magnitude required
a very strong effort by the Planning and Zoning Commission and the Inland
Wetlands Agency during the site plan review period. The day to day building plan review, progress
inspections, and certification has placed demands on key regulatory staff. Jim Taylor and Brett Stoddard
from the Building Department; Neil Angus
from the Planning Department, Earl Provencher from
the North Thompsonville Fire Department; and Debbie Caronna
from the North Central District Health Department deserve recognition.. MassMutual and
their contractors have offered the highest praise for the professionalism of
all public staff.
When Precision Camera came to
Enfield less than 3 years ago from
Chicopee, MA, they employed 49 people and
repaired 70,000 cameras per year. The
company now employs 175 people and repair 7,000 per week. The company purchased and renovated
#3 Anngina
Drive to accommodate growth; they later purchased
#1 Anngina
Drive. They have recently
leased #7 Anngina which has over 100 parking spaces
to meet their parking and production needs.
Be advised that this is not the end for this company's expansion in
Enfield.
A Springfield, MA company has a signed Purchase and
Sale Agreement on a large
Enfield manufacturing facility. Since it hasn't officially closed, they will
remain unidentified. The company has met
with Enfield economic development, human resources, and finance people
to get an understanding of the differences between CT and MA operations. This is a manufacturing company with 100
employees with strong growth potential.
We are optimistic that a fall move will take place.
The phase-in of production at Eppendorf Manufacturing is going according to
plan. Once the building was renovated,
two machines were installed to commence production. Three more sophisticated machines were
installed in May. Five more machines
will be in production in August. There
will be a total of 20 machines operating by the end of the year. With each new machine, more trained operators
are employed. The company will continue
to ramp up with support staff as the operation progresses. And this is the first phase.
The Crowne
Plaza Hotel, formerly the Radisson, had a grand opening celebration on August
25, 2005. The new owners work at the hotel and are
hands-on operators. The conversion to a
Crowne Plaza required that the owners undertake
a Property Improvement Plan that was based on an
inspection and report by Inter Continental Hotel Group. The 18 page PIP required improvements
including ADA related upgrades to rooms, repairs to swimming pools, replacement
of signage, lobby improvements, renovations to function rooms, new finishes for
elevators, replacement of HVAC units, new decorative standards in guest rooms,
and new color palette to signify a brand change. All improvements in the PIP had to be
complete prior to approving the Crowne Plaza name.
The construction value of
building permits is an indication of economic activity. Through seven months of the calendar year,
the Enfield Building Department has issued 1,338 separate permits with a
construction value of $25,363,511. There
are several significant projects yet to be counted. They include Best Buy, Outback Steakhouse,
the recently approved medical building on Elm, the planned drug store and bank
at Shaker and Elm. It is shaping up to
be another impressive construction season.
Think it's been unusually warm this
year? The above building permits include
$313,373. for 48 swimming pool permits, or an
average of $6,528 per pool permit.
Behind the scenes there are
development entities studying over 300 acres of land for possible
residential or industrial development in several locations in town. In one case, a seasoned developer is
examining the purchase of industrial land for a master planned project. In another, a housing developer is studying
sites now zoned Industrial, for conversion to Residential. In a third, a company is planning to sell an
industrial parcel. This preliminary work
has not reached a public plan review stage, but could have a substantial impact
on land development in Enfield.
Planning and economic development
offices will work together to define the potential impacts. If waterlines are extended in the
northeastern part of town, it could result in many homes. We need to be mindful of cost to schools and
government services.
Reviewing zone change requests
from Industrial to Residential is an important issue from an economic
development perspective. The shortage of
land for industrial sites becomes more acute each year. Some industrial land is not acceptable for
modern industrial use. It may lack
infrastructure, have less than desirable access, have too much wetlands, or conflict with adjacent uses. However, our finite industrial land supply
must be protected for the benefit of tax base growth and job creation.
The plans for developing a restaurant
and hotel on Parcel BR-1 have been submitted to the Town's Inland Wetlands
Agency and the Zoning Board of Appeals.
The developers hope for plan approval this fall. If approved, they will begin site work this
year. They must "surcharge"
the building pads for the hotel and restaurant to provide a suitable stable
soil condition for structural foundations.
This involves placing fill and allowing it to settle.
The Northgate public improvements
are under construction. Shortly
after the Town Council approval of the sale of a small piece of land to MassMutual, the Town DPW and engineering
staffs geared up to let the sidewalk construction contract along
Bright Meadow Boulevard and down Rt. 5 to
Willard Street.
This is the first phase of a larger improvement effort.
The MetroHartford
Alliance is lead agency for a Comprehensive Economic Development Strategy
(CEDS). The Austin, Texas firm of Angelou Economics is
conducting the study. The consultants
began the study with an informal dinner in Enfield at the Hazard Grille to solicit
ideas from Town representatives and Frank Gulluni of Asnuntuck.
A desirable goal is to provide the
new Town Council with information to make a decision about the future of the
Higgins School property.
It's an eyesore and is likely to get worse if the status quo is
maintained.
To change direction on Higgins, the
Town Council needs to be informed about the current environmental situation
and understand the physical condition of the building. This will help all parties to understand that
an action plan is desirable.
In addition, the policy makers
need to be briefed on building size, floor plans, site information, and
allowable uses per the zoning ordinance.
There has
been some staff conversations about the possible options for the future of
Higgins. Here's a few of the ideas:
(1) Conduct an RFP to entice a
private developer to completely renovate the building. (There has been casual
interested expressed for housing).
(2) Allow private renovation
and some new construction that helps the economics of a project.
(3) Demolish the building and
market a prepared site for redevelopment.
(4) Demolish the building and
keep the site in public ownership for future use.
(5) Public renovation of the
building for public use.
(6) The long shot:
rehabilitate Higgins to replace the Lamagana Center and clear the current center
for Strand Parking.
The Higgins property is important
to Thompsonville improvement efforts.
Hopefully, a plan of action will be a priority in 05-06
Visits to Enfield businesses this June demonstrated that all
business activity operates in an international business environment. The demand for raw materials, i.e., steel by China, keeps commodity prices high for
local businesses. Competition from
Eastern Europe, India, China, and Mexico requires local businesses to invest
in technology to keep competitive. The
improvements in technological know-how in those same countries force local
companies to impose cost containment strategies or find new business
opportunities to remain viable.
The sale of the Casual Corner
chain is a blow to Enfield. We do
not know the potential job loss details yet.
But two facts are clear, Casual Corner is the largest component of the
Retail Brand Alliance business and that many Enfield residents are employed at RBA. Our hope is that RBA will grow Brooks
Brothers and others to retain an excellent and loyal workforce.
There is progress to report from
the Community Development office.
Two bids have been received for general contracting services for the
North School renovation.
The first phase of the project came in at $164,665. The owner will be seeking permits in the next
few weeks. The CD office has been beating
the bushes to get contractors interested.
Peter Bryanton,
the CD Director, found a backlog of housing rehabilitation projects upon his
arrival in Enfield.
The rap on the Town was that it was slow to complete rehab projects, and therefore,
built surpluses in the rehab account. He
has managed to expedite production and, in fact, is working closely with DECD
to apply for a new round of rehab funding.
Our state CD program rep is very pleased with Enfield's progress and superior compliance
with a very complex body of regulations.
The CD staff is attending training
on the rules involved with CDBG program operations. They must stay current on lead paint
procedures, new environmental study requirements, and wage requirements. Over the years, the rules governing the use
of CD funds have added additional costs to projects to the point where the CD
dollars buy less. The advantage of these
funds is being lost due to the cost associated with the regulations.
The Yankee Bait and Tackle
project is making progress. The
second floor has been gutted and the owners are expanding their kayak
lines. They are making exterior building
repairs. A long neglected property is
showing signs of new life.
A town level economic development
office must work closely with regional and state peers. The Enfield ED office reaches out on a
regular basis for assistance and advice.
You should know that the professionals at the State Department of
Economic and Community Development, Connecticut Economic Resource Center, MetroHartford Alliance, and Connecticut Economic
Development Association are always there and helpful.
For example: CERC worked closely with an out of
state prospect likely to move to Enfield.
Northeast Utilities has visited Enfield businesses whenever requested. CEDAS is a great discussion forum for
important issues, e.g., eminent domain. MetroHartford is the lead in the CEDS and is a close
Enfield partner. These resources help expand the local
capability
Respectfully submitted,
Raymond L. Warren, Director
of Economic Development